Construction Process
-
removing old existing windows
-
-
after removing old false ceiling
-
reducing the size of the windows opening, in order to control the natural light, and energy transition
-
-
using still bars in new exterior wall. to connect the old structure
-
covering new brick walls with cement mortar, internal and external
-
implementing the steel structure of new internal walls
-
-
completing new internal walls with plasterboards
-
-
-
101 new UPVC double sided windows(1.3 k value) arrived from Poland
-
installing new windows
-
using second hand tiles as a flat cover on old sills
-
-
second floor internal division is ready
-
installation of false ceiling
-
-
-
covering the old exterior walls, with plasterboard
-
-
installing new water network
-
installing hidden water tank for toilets
-
toilets piping
-
toilets pavement installation
-
toilet internal division with waterproof plasterboard
-
-
painting & electrical installation
-
-
-
-
-
-